BY | September 11, 2012

Chennai, (IANS) A team of officials from the Indian atomic energy regulator was Monday doing the final studies of the first reactor at Kudankulam Nuclear Power Project (KNPP), said a top official.

“Our team of officials is now at Kudankulam, poring over reports and studying the finer details of the reactor systems to satisfy themselves before giving the final clearance for the loading of the fuel,” S.S. Bajaj, chairman, Atomic Energy Regulatory Board (AERB) told IANS on phone from Mumbai.

He said that if all goes well, the fuel loading would happen this week.

India’s atomic power plant operator Nuclear Power Corporation of India Ltd (NPCIL) is setting up the KNPP at Kudankulam in Tamil Nadu’s Tirunelveli district, around 650 km from here with two Russian-made VVER 1000 reactors.

The first unit is in advanced stage of commissioning, with AERB giving its nod Aug 10 to load 163 of the enriched uranium fuel bundles in the reactor.

After the reactor is fuelled, activities to approach first criticality-starting fission chain reaction, for the first time in a reactor, will be taken up. Then the power generation will be gradually scaled up on AERB’s permission based on the results of various studies.

“After fuel loading, NPCIL will have to do certain tests. Based on the test results, we will give clearance for criticality. Following that, the raising of power generation will be permitted in stages and the reactor will have to operate at 100 percent satisfactorily for sometime, Bajaj said.

The AERB would then issue NPCIL the operational licence for the first unit of KNPP.

The KNPP is an outcome of the Inter-Governmental Agreement (IGA) signed between India and the erstwhile USSR in 1988. However, the project construction began in 2001.

In a written reply in the Lok Sabha, Minister of State in the Prime Minister’s Office V. Narayanasamy said: “The project was initially delayed due to non-sequential receipt of equipment from the Russian Federation and subsequently due to local protests impeding the work from September 2011 to March 19, 2012.”

According to NPCIL officials, the fuel-loading process would take around one week and the observers from International Atomic Energy Agency (IAEA) may come at the start or at the end as KNPP reactors fall under the safeguard agreement that was signed with the former.

RELATED

By S Ahmad   Source: NVONews.COm   Akhtarul Iman who choose to announce his pull out of the election fray from Kishanganj as Janta Dal United candidate is being put to all the moral yardsticks available in the book. As it is easy to use his name, just...

akhtarul iman

Mamata accuses Congress, CPI-M for EC’s transfer of officers in WB     Kolkata: West Bengal chief minister Mamata Banerjee is taking on almost everyone during the election. She has said that all the opposition parties in the state have ganged up to beat her...

Arrest warrant issued against Giriraj Singh for communal comment   Patna: Almost a week after making inflammatory remarks in a public rally, BJP leader and its candidate from Nawada Lok Sabha seat Giriraj Singh has been issued an arrest warrant by a Bokaro...

giriraj singh1

HDFC Bank denies report of JM Financial merger   Mumbai: After posting its lowest ever net profit in any quarter in the 4th quarter, the company seems to be perturbed by a news report that the JM Financial stock was set to merge with Mumbai based...

RBI for 2-stage authentication due to online banking frauds   The number of online frauds is going up pretty fast. Almost on a daily basis dozens of such frauds are reported to the police and banks.   The criminals are becoming hi-tech and they are cleverly...

ATM

Sony Xperia M2 Dual with 4.8-inch display, 8MP camera @ Rs 21990   For Rs 21,990 you can lay your hands on Xperia M2 Dual smartphone. This mid-range mobile has been launched by Sony keeping in mind the Indian market.     The dual-SIM variant of the...